Glossary

a
Acceptance

The act of taking custody based on satisfactory verification.

Acceptance Criteria

The requirements and conditions that must be met for acceptance of the deliverables.

Acceptance Test

Tests conducted in accordance with an approved verification plan and approved test procedures. Tests are best conducted by an independent organization and witnessed by a representative of the buyer for compliance with the test procedure and verification plan.

Acceptance Test Procedure (ATP)

Detailed step-by-step instructions for the set-up, operation, and evaluation of tests. The procedure includes the approach to sampling and statistical quality control.

Accrued Cost

A cost that is incurred all at once at a certain time in a project or gradually, for instance, over the entire time a task is being worked on.

Acquisition

The obtaining under contract of supplies and services to meet the needs of a project.

Acquisition Plan

The document that describes the approach for acquisition. It defines competitive or sole source, schedule, funding, manpower, facilities, risk, etc. Also called the System Acquisition Plan.

Activity

An element of work performed during the course of a project. An activity normally has an expected duration, expected cost, and expected resource requirements. Activities are often subdivided into tasks.

Activity Definition

Identifying the specific activities that must be performed in order to produce the various project deliverables.

Activity Description (AD)

A short phrase or label used in a project network diagram. The activity description normally describes the scope of work of the activity.

Activity Duration Estimating

Estimating the number of work periods which will be needed to complete individual activities.

Activity Sequencing

Identifying and documenting dependencies among schedule activities

Activity-On-Arrow (AOA)

See arrow diagramming method.

Activity-On-Node (AON)

See precedence diagramming method.

Actual Cost (AC)

Total costs incurred that must relate to whatever cost was budgeted within the planned value and earned value (which can sometimes be direct labor hours alone, direct costs alone, or all costs including indirect costs) in accomplishing work during a given time period. See also earned value.

Actual Cost of Work Performed (ACWP)

This term has been replaced with the term actual cost.

Actual Finish Date (AF)

The point in time that work actually ended on an activity. (Note: in some application areas, the activity is considered "finished" when work is "substantially complete.")

Actual Start Date (AS)

The point in time that work actually started on an activity.

Administrative Closure

Generating, gathering, and disseminating information to formalize phase or project completion.

Analogous Estimating

An estimating technique that compares a project or activity to a similar previous project or activity.

Application Area

A category of projects that have common elements not present in all projects. Application areas are usually defined in terms of either the product of the project (i.e., by similar technologies or industry sectors) or the type of customer (e.g., internal vs. external, government vs. commercial). Application areas often overlap.

Apportioned Effort

Effort that is not itself readily divisible into short-span work packages but which is related and proportional to measured effort in other work packages. Project management overhead is an example. Also see Discrete Effort

Apportioned Task

A task that is dependent on or related to the performance of another task.

Arrow

The graphic presentation of an activity. See also arrow diagramming method.

Arrow Diagramming Method (ADM)

A network diagramming technique in which activities are represented by arrows. The tail of the arrow represents the start and the head represents the finish of the activity (the length of the arrow does not represent the expected duration of the activity). Activities are connected at points called nodes (usually drawn as small circles) to illustrate the sequence in which the activities are expected to be performed. See also precedence diagramming method.

As-of Date

See data date.

Assumptions

Assumptions are factors that, for planning purposes, are considered to be true, real, or certain. Assumptions affect all aspects of project planning, and are part of the progressive elaboration of the project. Project teams frequently identify, document, and validate assumptions as part of their planning process. Assumptions generally involve a degree of risk.

Assumptions analysis

A technique that explores the assumptions' accuracy and identifies risks to the project from inaccuracy, inconsistency or incompleteness of assumptions.

Award

The assignment of work under Contract.

Award Fee

A contract fee provision used to motivate a contractor to respond to issues that are assigned and measured periodically and subjectively. The contract specifies award fee periods, usually six to nine months long. The award fee criteria are negotiated prior to the start of the award fee period, providing the buyer flexibility to change the incentive emphasis as the project evolves. The determination is made unilaterally by the buyer and is not subject to the legal disputes clause provisions.